Andalusian Green Hydrogen Valley, with two main locations, Huelva (include ONUBA and THARSIS projects) and Cádiz (CARTEIA Project)

Moeve’s "Andalusian Green Hydrogen Valley" will install 2 GW of electrolysis. In Huelva: ONUBA (400 MW H₂+ammonia with Fertiberia), THARSIS (200 MW H₂+methanol), plus 400 MW under discussion. In CARTEIA, projects with EDP (H₂) and Yara (ammonia) aim to decarbonise local industries, transport sector, and North Europe
LEAD DEVELOPER

Moeve

PROJECT PARTNERS

In ONUBA, Fertiberia, Enagas Renovable and Alter Enersun // In CARTEIA, EDP Renovables and Yara Clean Ammonia
We are supporting Enagas, Spanish TSO, to develop the H2pipeline infrastructure. Also, conversations with ports and company H2 infrastructures as Gasunie, Vopak and Port of Rotterdam will facilitate the storage and distribution of H2 and its derivatives
ONUBA, renewable hydrogen and ammonia production (end use): Decarbonised conventional fuels, HVO, Fertiberia decarbonisation and transport sector/THARSIS, Methanol Plant: maritime /CARTEIA, renewable ammonia production (end use): fertilisers & maritime

MAIN POLITICAL SPONSORS

For both projects we have collected several letters of support from public and private entities: town halls, regional authorities, technological associations, syndical organizations, banks, heavy industry, transport sector, fertilizer sector, etc.

MAIN LOCATION

Spain

OTHER LOCATIONS

Yes

Project details

H2 PRODUCTION VOLUME

[T/year]:

300,000

INVESTMENT VOLUME

[M€]:

3,000.00
FUNDING
VALUE CHAIN COVERAGE

PRIMARY ENERGY SOURCING

  • Electricity from solar PV
  • Electricity from onshore wind

H2 PRODUCTION

  • Water electrolysis with PEM electrolyser
  • Water electrolysis with ALK electrolyser
  • SMR
  • SMR with CC(U)S
  • External sourcing from outside the H2 valley - Regional

H2 STORAGE

  • Cylinder - Compressed H2
  • Cylinder - Methanol
  • Cylinder - Ammonia

H2 TRANSPORT

  • Pipeline - Compressed H2
  • Pipeline - Ammonia
  • Ship - Methanol
  • Ship - Ammonia

H2 DISTRIBUTION FOR MOBILITY

  • HRS 700 bar
  • HRS 350 bar
END USES

MOBILITY

  • Buses
  • Other

ENERGY

INDUSTRIAL FEEDSTOCK

  • Supply to chemical industry (e.g. fertilizer production)
  • Supply to refineries
  • Supply to steel industry

Project timeline

CURRENT STATUS:

pre-FID (planning, engineering, de-risking, etc.)

2014

Start of project development

Project finalization

2035


KEY SUCCESS FACTORS

PROJECT DEVELOPMENT PHASE

  • Business model/business case development

  • Regulatory provisions

  • Permitting and authorization procedures

  • Funding

  • Experienced staff

    not only in H2 but power (key in this new sector)

  • Local public acceptance

  • Project's business case

  • Stakeholder cooperation

  • Risk sharing mechanisms between project partners

  • Project's governance model

COMMERCIAL AND FINANCING PHASE

  • Applying for public subsidy/grant schemes

  • Securing private investors

  • Securing public financial support (subsidy/grant)

  • Preparing documentation for a due diligence process

  • Putting a de-risking framework in place

  • Securing customer commitments to de-risk the financial model

N.A.: Not available. This is possible due to two reasons: a) the Hydrogen Valley chose to not publicly display the data or b) the Hydrogen Valley did not answer the specific question in the associated survey.