REFHYNE 2

REFHYNE 2 will install a 100 MW PEM electrolyser at the Shell Rheinland Energy and Chemicals Park in Germany, using renewable power to produce green hydrogen and oxygen, which will be fed-in to the existing refinery networks to decarbonise refinery operations. The electrolyser will be based on a state of the art pre-engineered 10MW electrolyser trains..
LEAD DEVELOPER

Shell

PROJECT PARTNERS

ITM Power, ITM GmbH, Linde, ITM Linde Electrolysers, Shell, SINTEF, Tecnalia, Element Energy, ERM France, Concawe
Shell

MAIN POLITICAL SPONSORS

N/A

MAIN LOCATION

Germany

OTHER LOCATIONS

No

Project details

H2 PRODUCTION VOLUME

[T/year]:

12,000

INVESTMENT VOLUME

N.A.

FUNDING
VALUE CHAIN COVERAGE

PRIMARY ENERGY SOURCING

H2 PRODUCTION

  • Water electrolysis with PEM electrolyser

H2 STORAGE

H2 TRANSPORT

  • Pipeline - Compressed H2

H2 DISTRIBUTION FOR MOBILITY

END USES

MOBILITY

  • Cars
  • Buses
  • Trucks

ENERGY

INDUSTRIAL FEEDSTOCK

  • Supply to refineries

Project timeline

CURRENT STATUS:

pre-FID (planning, engineering, de-risking, etc.)

2014

Start of project development

N.A.

Project finalization

2035


KEY SUCCESS FACTORS

PROJECT DEVELOPMENT PHASE

  • Business model/business case development

  • Technological readiness/technological performance (e.g. availability, efficiency, duration/lifetime)

  • Regulatory provisions

    Clear legal boundaries incl. legal certainty needed for the project (eg RED II)

  • Project's business case

COMMERCIAL AND FINANCING PHASE

  • Securing public financial support (subsidy/grant)

  • Building a financial model

N.A.: Not available. This is possible due to two reasons: a) the Hydrogen Valley chose to not publicly display the data or b) the Hydrogen Valley did not answer the specific question in the associated survey.