Oulu Green Hydrogen Park

Energiequelle’s Oulu Green Hydrogen Park is a planned renewable-powered facility in northern Finland. It will produce green hydrogen through a phased rollout, starting with a 5 MW electrolyser and heavy vehicle refueling station. Future phases will scale capacity to 500 MW. As part of a broader 1500 MW hydrogen hub in Oulu, the project supports clean energy goals and positions Finland for hydrogen export leadership.
LEAD DEVELOPER

Energiequelle

PROJECT PARTNERS

• For Phase One of the project, which focuses on a hydrogen refuelling station, we are looking to partner with a party that can help develop the refuelling infrastructure. Our role will concentrate on the production of RFNBO-certified hydrogen.
• For Phases Two and Three, we are currently exploring options for producing raw hydrogen and supplying it to another chemical plant. This plant would then produce a clean RFNBO-certified derivative, such as e-methanol or e-ammonia, leveraging the abundan

MAIN POLITICAL SPONSORS

Business Oulu, City of Oulu, Gasgrid Oy, Energiequelle GmbH

MAIN LOCATION

Finland

OTHER LOCATIONS

No

Project details

H2 PRODUCTION VOLUME

[T/year]:

71,600

INVESTMENT VOLUME

[M€]:

850.00
FUNDING
VALUE CHAIN COVERAGE

PRIMARY ENERGY SOURCING

  • Electricity from solar PV
  • Electricity from onshore wind
  • Hydropower

H2 PRODUCTION

    H2 STORAGE

    H2 TRANSPORT

    • Pipeline - Compressed H2
    • Trucking - Compressed H2
    • Trucking - Liquid H2
    • Trucking - Methanol
    • Trucking - Ammonia
    • Ship - Compressed H2
    • Ship - Liquid H2
    • Ship - Methanol
    • Ship - Ammonia

    H2 DISTRIBUTION FOR MOBILITY

    • HRS 350 bar
    END USES

    MOBILITY

    • Buses
    • Trucks
    • Forklifts
    • Trains
    • Ships

    ENERGY

    • Other

    INDUSTRIAL FEEDSTOCK

    • Supply to chemical industry (e.g. fertilizer production)
    • Supply to refineries
    • Supply to steel industry
    • Supply to other industries

    Project timeline

    CURRENT STATUS:

    Feasibility study ongoing

    2014

    Start of project development

    Project finalization

    2035


    KEY SUCCESS FACTORS

    PROJECT DEVELOPMENT PHASE

    • Business model/business case development

    • Technological readiness/technological performance (e.g. availability, efficiency, duration/lifetime)

    • Regulatory provisions

    • Permitting and authorization procedures

    • Political backing and buy-in

    • Funding

    • Local public acceptance

    • Project's business case

    • Stakeholder cooperation

    COMMERCIAL AND FINANCING PHASE

    • Applying for public subsidy/grant schemes

    • Securing private investors

    • Securing public financial support (subsidy/grant)

    • Building a financial model

    • Preparing documentation for a due diligence process

    • Putting a de-risking framework in place

    • Securing customer commitments to de-risk the financial model

    N.A.: Not available. This is possible due to two reasons: a) the Hydrogen Valley chose to not publicly display the data or b) the Hydrogen Valley did not answer the specific question in the associated survey.