Cluster NortH2

Hydrogen Valleye situated in Mid and North Jutland, Denmark
LEAD DEVELOPER

Evida and Gas Storage Denmark

PROJECT PARTNERS

Eurowind Energy and GreenLab
Evida and Gas Storage Denmark
GreenLab

MAIN POLITICAL SPONSORS

MAIN LOCATION

Denmark

OTHER LOCATIONS

No

Project details

H2 PRODUCTION VOLUME

N.A.

INVESTMENT VOLUME

N.A.

FUNDING
VALUE CHAIN COVERAGE

PRIMARY ENERGY SOURCING

  • Electricity from solar PV
  • Electricity from onshore wind

H2 PRODUCTION

    H2 STORAGE

    • Cavern - Compressed H2

    H2 TRANSPORT

    • Pipeline - Compressed H2

    H2 DISTRIBUTION FOR MOBILITY

    END USES

    MOBILITY

    • Trucks

    ENERGY

    • Hydrogen supply to gas-fired power plants

    INDUSTRIAL FEEDSTOCK

    • Supply to chemical industry (e.g. fertilizer production)
    • Supply to other industries

    Project timeline

    CURRENT STATUS:

    pre-FID (planning, engineering, de-risking, etc.)

    2014

    Start of project development

    N.A.

    Project finalization

    2035


    KEY SUCCESS FACTORS

    PROJECT DEVELOPMENT PHASE

    • Business model/business case development

    • Regulatory provisions

    • Permitting and authorization procedures

    • Funding

    • Project's business case

    • Stakeholder cooperation

    • Risk sharing mechanisms between project partners

    COMMERCIAL AND FINANCING PHASE

    • Applying for public subsidy/grant schemes

    • Securing private investors

    • Securing public financial support (subsidy/grant)

    • Building a financial model

    • Putting a de-risking framework in place

    • Securing customer commitments to de-risk the financial model

    N.A.: Not available. This is possible due to two reasons: a) the Hydrogen Valley chose to not publicly display the data or b) the Hydrogen Valley did not answer the specific question in the associated survey.