TRIERES

Country
Greece

TRIĒRĒS Valley starts as a small scale Valley but has a tremendous upward perspective over a large part of the Balkans, South-Eastern Europe and the wider area of Eastern Mediterranean. The Valley will be built around the nucleus of MOH’s Corinth Refinery, with an annual production of 2,410 tons of Green Hydrogen consumed in mobility, shipping, energy and industry sectors. The participation of the local and regional governments assures the realisation of the TRIĒRĒS Valley project.

Lead developer Motor Oil (Hellas)
Project partner

Overarching / General

Region of Peloponnese, Greece | Municipality of Loutraki-Perachora-Agioi Theodoroi, Greece

H2 production

Motor Oil (Hellas), Public Power Corporation SA

H2 transportation, storage & distribution

Motor Oil (Hellas), AVINOIL, CORAL GAS

H2 end use

LPC , Olympia Odos, Piraeus Port Authority, Municipality of Loutraki-Perachora-Agioi Theodoroi, Road Transport SA, AEDIK, ECOFERRY, DIORIGA GAS, FULGOR SA

Locations
Greece | Multicity

Project details

Production volume

H2 production from electrolysis

2,410 H2 tons/year

Final products

2410.00 tons/year of H2

H2 color

Green

Total electrolyser capacity

50.00 MW

Total investment (CAPEX)

219.80 EUR m

Value chain coverage

Primary energy sourcing

Grid - 51.50 MW

H2 production

Alkaline water (ALK) electrolyser – 50.00 MW

H2 Storage

Artificial - 1123.00 tons

H2 transport

Pipeline Trucking

H2 distribution for mobility

350 bar (for cars and similar vehicles) 700 bar (for trucks and similar vehicles)

End use

Mobility

Road Shipping

Energy

Stationary fuel cells for distributed generation Hydrogen supply for injection into gas grid

Industry

Refineries

Project timeline

Current status: Construction started

Planned timeline for First built out stage

Q3 2023 Project initiated
Q1 2024 Concept study completed
Q3 2024 Feasibility study completed
Q3 2025 FEED completed
Q3 2025 Final Investment Decision taken
Q4 2025 Construction started
Q3 2027 In operations

Current main activities

Site preparation and civil works in progress
Delivery and installation of key equipment underway