HyBayern
Country
Germany
Compilation of three admin. districts (LA-EBE-M), transport companies, energy providers, industry, trade and crafts. Implementation of closed hydrogen cycle generating, distributing and using emission-free "green hydrogen".
Lead developer
Hy2B GmbH
Project partner
Overarching / General
Local governments, secretaries
H2 production
Hy2B GmbH
H2 transportation, storage & distribution
Transportation companies
H2 end use
Bus companies/Public transport
Project details
Production volume
H2 production from electrolysis
400
H2 tons/year
Final products
400.00
tons/year of H2
H2 color
Green
Total electrolyser capacity
5.00
MW
Total investment (CAPEX)
30
EUR m
Value chain coverage
Primary energy sourcing
Grid - 5.00 MW
H2 production
Alkaline water (ALK) electrolyser – 5.00 MW
H2 Storage
Other - 8.00 tons
H2 transport
Trucking
H2 distribution for mobility
350 bar (for cars and similar vehicles)
End use
Mobility
Road
Project timeline
Current status:
In operations
Planned timeline for Final built out stage
Q3 2019
Project initiated
Q2 2021
Concept study completed
Q2 2021
Feasibility study completed
Q4 2021
FEED completed
Q4 2021
Final Investment Decision taken
Q3 2022
Construction started
Q2 2024
In operations
Current main activities
First volumes delivered to offtakers or injected into the network
Monitoring of performance (technical, commercial, environmental) and continuous optimization
Operations and maintenance processes fully implemented