H2V Rasina

Country
Serbia

Rasina Hydrogen Valley initiative aims to implement green hydrogen value chain ecosystem in Western Serbia by: a) an annual production of 500t of renewable hydrogen; b) deployment of H2 mobility through building a HRS and retrofitting 15 busses and trucks; c) generating 2x200kW electricity from HFC stacks and blending with natural gas; d) replacing 200tpa of black-hydrogen in existing industrial productions; and e) capacity building and new green hydrogen deployment courses in a high-school.

Lead developer H2V Rasina Hydrogen Valley
Project partner

Overarching / General

H2V Rasina Hydrogen Valley

H2 production

H2V Rasina Hydrogen Valley doo

H2 transportation, storage & distribution

Messer Tehnogas doo

H2 end use

King Gas doo; Messer Tehnogas doo

Locations
Serbia | Krusevac
Serbia | Belgrade

Project details

Production volume

H2 production from electrolysis

500 H2 tons/year

H2 color

Green

Total electrolyser capacity

3.50 MW

Total investment (CAPEX)

51 EUR m

Value chain coverage

Primary energy sourcing

Photovoltaics - 20.00 MW Dedicated onsite renewables - 20.00 MW

H2 production

Polymer electrolyte membrane (PEM) electrolyser – 3.50 MW

H2 Storage

Artificial - 2.00 tons

H2 transport

Trucking

H2 distribution for mobility

350 bar (for cars and similar vehicles)

End use

Mobility

Road

Energy

Hydrogen supply for injection into gas grid

Industry

Chemical industry (incl. fertilizer production) Other

Project timeline

Current status: Feasibility study completed

Planned timeline for Final built out stage

Q2 2025 Project initiated
Q3 2025 Concept study completed
Q2 2026 Feasibility study completed
Q4 2026 FEED completed
Q4 2027 Final Investment Decision taken
Q1 2028 Construction started
Q4 2028 In operations

Current main activities

Stakeholder commitment and MoUs with key partners (e.g., industry, municipalities, utilities)