Andalusian Green Hydrogen Valley, with two main locations, Huelva (1 GW) and Cádiz (1 GW)

Country
Spain

Moeve is developing the Andalusian Green Hydrogen Valley, a 2 GW project, in Huelva (1GW) and Cádiz (1 GW) hubs, to produce renewable hydrogen and derivatives such as ammonia, methanol and eSAF. The first 300 MW phase has reached FID. The Valley will scale up through successive phases and support European corridors, including H2Med and South North maritime hydrogen routes.

Lead developer Moeve
Project partner

Overarching / General

The Andalusian Green Hydrogen Valley unites partners across all the value chain in its Huelva and Cádiz hubs, and it is supported by letters from public and private stakeholders at Spanish, European and international levels.

H2 production

The first phase will be developed with partners, including Enagás Renovable. The following phases are being discussed with national and international stakeholders helping anchor the Valley’s renewable hydrogen production and supply hard to abate sectors.

H2 transportation, storage & distribution

We support Enagás, the Spanish TSO, in developing the hydrogen pipeline network, while ongoing discussions with European ports and companies such as Gasunie and Vopak will facilitate the storage and distribution of hydrogen and its derivatives.

H2 end use

The Valley will produce renewable derivatives such as ammonia, methanol and eSAF to supply hard to abate sectors and help refineries, transport and industry comply with RED III targets.

Locations
Spain | Huelva, Palos de la Frontera
Spain | Cádiz, San Roque

Project details

Production volume

H2 production from electrolysis

300,000 H2 tons/year

Final products

H2
E-ammonia
E-methane
E-methanol
E-SAF

H2 color

Green

Total electrolyser capacity

400.00 MW

Total investment (CAPEX)

5,000 EUR m

Value chain coverage

Primary energy sourcing

Photovoltaics Grid Dedicated onsite renewables

H2 production

Alkaline water (ALK) electrolyser – 300.00 MW Polymer electrolyte membrane (PEM) electrolyser – 100.00 MW

H2 Storage

Artificial

H2 transport

Pipeline Shipping

End use

Mobility

Aviation Shipping

Energy

Hydrogen supply for injection into gas grid

Industry

Refineries Chemical industry (incl. fertilizer production) Steel industry

Project timeline

Current status: Final Investment Decision taken

Planned timeline for First built out stage

Q1 2023 Project initiated
Q3 2023 Concept study completed
Q1 2024 Feasibility study completed
Q1 2025 FEED completed
Q1 2026 Final Investment Decision taken
Q1 2026 Construction started
Q2 2029 In operations

Current main activities

Full financial close reached with public and/or private investors
Procurement of major components (e.g., electrolysers, compressors) initiated