Agder Hydrogen Hub

Country
Norway

20 MW green hydrogen production (2600 tons/year) in Kristiansand, Norway, under construction with commissioning in Q4 2026 with compressed hydrogen. Expansion of +40 MW (60 MW in total, 7200 tons/year) in 2028, with possibilities for both compresed and liquified hydrogen. The project is owned 100% by Greenstat AS.

Lead developer FDE & Greenstat
Project partner

Overarching / General

ENOVA

H2 production

ITM (electrolyzer), Hoerbiger (compressor)

Locations
Norway | Kristiansand

Project details

Production volume

H2 production from electrolysis

2,600 H2 tons/year

Final products

2600.00 tons/year of H2

H2 color

Green

Total electrolyser capacity

40.00 MW

Value chain coverage

Primary energy sourcing

Grid - 20.00 MW Dedicated onsite renewables

H2 production

Polymer electrolyte membrane (PEM) electrolyser – 20.00 MW

H2 distribution for mobility

350 bar (for cars and similar vehicles)

End use

Mobility

Road Shipping

Project timeline

Current status: Construction started

Planned timeline

Q3 2024 Construction started
Q1 2027 In operations

Current main activities

Site preparation and civil works in progress
Delivery and installation of key equipment underway